Construction progress of Park Royal as of the end of July 2024.
HOUSE A011
Currently, the builders have completed the construction of the 7th floor in the first section of the building. The building consists of 9 floors.
We have also completed the reinforcement and concreting of the monolithic floor of the 6th floor of the first section.
In the second section, the installation of horizontal formwork for the floor slab of the 7th floor has begun.
In the third section, concreting works are underway on the vertical structures of the 1st floor, with 50% of the work completed.
Concreting of the foundation slab is underway in the fourth and fifth sections.
HOUSE A012
The builders continue to fill the pit for the second house (A012) of the first stage of construction.
The installation of utilities is also underway: ventilation units are currently being installed in the first and second sections.