It's hot not only outside the windows, but also at the Park Royal construction site! We are thrilled to share the news as of 15 July 2024.
HOUSE A011
The 5th floor of the first section of the building is under construction.
The reinforcement and concreting of the monolithic floor slab on the 4th floor of the first section has been completed.
In the second section, the installation of horizontal formwork for the floor slab of the 4th floor has begun.
In the third section, the reinforcement of the foundation slab has been completed.
Work is also underway to reinforce the vertical structures, and the installation of vertical formwork on the 1st floor for further concreting has begun.
HOUSE A012
At present, the builders are completing the filling of the pit for the second house (A012) of the first stage of construction.
Work continues on the installation of utilities: specialists are actively working on laying a power cable from the substation directly to the residential complex.